We use necessary cookies to make our website work. We'd also like to use optional cookies to understand how you use it, and to help us improve it.

For more information, please read our cookie policy.

This consultation document provides further information on costs that Heathrow Airport Limited (“HAL”) expects to incur in advance of receiving a development consent order (“DCO”) under the Planning Act 2008 for the expansion of Heathrow airport.

It outlines the approach to this early spending that we consider is in the best interest of consumers and the regulatory arrangements that should apply.

This consultation follows on from our July 2019 consultation on early costs and the regulatory timetable (CAP1819).

Status:
Current
Review comment:
-
Version:
1
Version date:
19-Dec-2019
View file:

This publication features in the following categories.