Sponsor: TAG Farnborough Airport
Last updated: 23 October 2024
Most recent update: The Farnborough Airspace Change post implementation review report has been completed and is currently under management review for approval.
Framework briefing held with organisations considering proposal of the change
|
15 Jun 2012 |
Sponsor external consultation document (with associated appendices)
|
12 May 2014 |
Sponsor's external consultation feedback report | 15 Jun 2014 |
Sponsor's formal airspace change proposal (date received by CAA) | 3 Jul 2015 |
Sponsor's additional consultation document | 2 Nov 2016 |
Sponsor's additional consultation feedback report | 14 Dec 2016 |
CAA letter to sponsor | 25 Aug 2017 |
Operational assessment by CAA | 12 Jul 2018 |
Initial consultation assessment by CAA | 12 Jul 2018 |
Addendum consultation assessment by CAA | 12 Jul 2018 |
Environmental assessment by CAA | 20 Jul 2018 |
Decision document ( CAP 1678) | 11 Jul 2018 |
In assessing the proposal and making the decision, the CAA has taken account of the following documents received from the sponsor:
|
|
Sponsor's acceptance letter of CAA decision | 17 Jul 2018 |
Change implementation date | 27 Feb 2020 |
AIRAC distribution date / AIP amendment | |
Sponsor's Post-Implementation Review analysis |
15 May 2023 |
CAA PIR assessment Updated 10 May 2024: The change sponsor has produced a revised version of Annex E of its Post-Implementation Review analysis which corrects some errors in Section 5 and includes a new Section 7 relating to controller’s use of controlled airspace and additional radar data analysis. This can be found in the Sponsor's Post-Implementation Review analysis section of the table below as ‘Annex E v1.1’. The CAA has continued to work with the sponsor and the key other airspace users in that part of southern England and fundamental airspace sharing arrangements are still being developed and reviewed to enable the best use of the airspace to be developed. These arrangements will seek to safely and efficiently accommodate aviation stakeholder’s requirements. You can keep abreast of further developments by monitoring the updates and associated documentation on our website or by signing up to SkyWise news alerts. Updated 5 October 2023: The Post-Implementation Review (PIR) work continues. Following the closure of the CAA’s 42-day feedback window, additional stakeholder responses continued to be received and are being included in the review. CAP1616 Appendix H, Post-implementation Review timescales indicate that at H7 (page 241), additional analysis of data and any need for the CAA to request further operational data from the change sponsor, may result in an extension to the analysis and delay the publication of the results of the review in its report. Updated 15 May 2023: The Post-Implementation Review (PIR) data has now been received from the sponsor and published. They can be found in the table below under 'Sponsor's Post-Implementation Review analysis'. The CAA now invite any stakeholders to submit their own observations via email to Airspace.Policy@caa.co.uk no later than Monday, 26 June 2023. The CAA will aim to produce a PIR review report within three months. This activity is not a review of the decision on the airspace change proposal, and neither is it a re-run of the original decision process. Upon completion of the CAA’s review, we may:
Updated 3 April 2023: The PIR data collection period finished on 31 March 2023. The sponsor must now analyse the data it has collected and prepare a detailed analysis of how the impacts of the change compare with the anticipated impacts set out in the airspace change proposal. For reasons including public holidays over the Easter period the sponsor has requested 42 rather than the usual 28 days to complete and publish its PIR data and the analysis of it required by CAP 1616. We have agreed to that request. Taking into account that stakeholders may have planned for a specific window for providing their comments on whether implementation of the change has had the impacts that were anticipated when the decision to agree the change was made, we have decided also to expand the stakeholder feedback window from 28 to 42 days. Updated 26 September 2022: Due to the impact of the Covid-19 pandemic on air operations around the globe, the commencement of the 12 month data collection period for the purpose of this PIR was delayed until 1 April 2022. The CAA’s ACP Post Implementation Review Data Request was provided to the sponsor, which the sponsor published on its web page. The PIR will follow the process set out in CAP 1616. However, as this ACP decision was made under the former airspace change process, CAP 725, we will use the methodology that applied at the time of the original decision when assessing the expected impacts against the actual impacts. This means we will use the Secretary of State’s Air Navigation Guidance 2014, as agreed with the Department for Transport. Post implementation reviews are a rigorous assessment by the CAA of whether the anticipated impacts and benefits, set out in the original airspace change proposal and decision, have been delivered and if not to ascertain why and to determine the most appropriate course of action. The CAA’s review will include an assessment of aircraft using Farnborough airport, of aircraft using the airspace that was the subject of the change and of aircraft flying in the vicinity of the airspace that was the subject of the change. The CAA has specified data requirements for the PIR that will enable that assessment. The CAA has received specific queries from stakeholders and confirms:
|
Provide page feedback
Please enter your comments below, or use our usual service contacts if a specific matter requires an answer.
Fields marked with an asterisk (*) are required.