Sponsor: Stansted Airport

Following very positive feedback and support during an extensive trial, Stansted Airport proposes the permanent introduction of the two trialled RNP1 SIDs, CLN1E and DET1D to complement the existing conventional procedures. The two procedures will reduce the number of people in the local area directly overflown by departing aircraft as a result of improved navigational accuracy.

Last updated: 09 September 2021

Framework briefing held with organisations considering proposal of the change 26 Jan 15

Sponsor external consultation document (with associated appendices)

1 Sep to 27 Nov 15
Sponsor's external consultation feedback report 19 Jan 16

Sponsor's formal airspace change proposal (date received by CAA)

3 Feb 16
Operational assessment by SARG TBD
Consultation assessment by SARG  
Environmental assessment by SARG  
Decision document(CAA change approval) 3 May 17

Change implementation date

17 Aug 17
AIRAC distribution date / AIP amendment 6 Jul 17
PIR initiation date 18 Aug 18

Sponsor's analysis

Post Implementation Review London Stansted RNP1 SIDs

 

CAA PIR assessment

PIR Feedback Form - London Stansted RNP1 SIDs

CAP2249 London Stansted RNAV SIDs (RNP1) PIR