Sponsor: Neart na Gaoithe (NNG) Offshore Wind Farm Limited (NNGOWL) and Inch Cape (IC) Offshore Limited (ICOL) assisted by Osprey Consulting Services Limited
NNGOWL and ICOL wish to respectively develop the NNG and IC wind farms located in the outer Firth of Forth to the east of Fife. The Sponsors have proposed a Transponder Mandatory Zone (TMZ) to mitigate the wind turbine effects on the RAF Leuchars Primary Surveillance Radar (PSR).
Last updated: 18 December 2017
Framework briefing held with organisations considering proposal of the change | 20 Jan 15 |
Sponsor external consultation document (with associated appendices) | 15 Jun to 7 Sep 15 |
Sponsor's external consultation feedback report | 01 Oct 15 |
Sponsor's formal airspace change proposal (date received by CAA) | 05 Oct 15 |
Operational assessment by CAA | 06 May 16 |
Consultation assessment by CAA | 29 Apr 16 |
Environmental assessment by CAA | 29 Mar 16 |
Decision document (CAA change approval) | 06 May 16 |
AIRAC distribution date / AIP amendment | TBC |
Change implementation date | TBC |
PIR initiation date | TBC |
Sponsor's analysis | |
CAA PIR assessment |