We use necessary cookies to make our website work. We'd also like to use optional cookies to understand how you use it, and to help us improve it.

For more information, please read our cookie policy.



Sponsor: NATS

Framework briefing held with organisations considering proposal of the change 22 Jan 2015
Sponsor external consultation document (with associated appendices) 31 Mar 2015
Sponsor’s external consultation feedback report 21 Jul 2015
Sponsor’s formal airspace change proposal (date received by CAA) 27 Jul 2015
Operational assessment by CAA 16 Nov 2015
Consultation assessment by CAA 09 Nov 2015
Environmental assessment by CAA 26 Aug 2015
Decision document (CAA change approval) Jan 2016
AIRAC distribution date/AIP amendment  
Change implementation date  
PIR initiation date  

Post Implementation Review, March 19

The purpose of the PIR is for the CAA, as the independent regulator, to assess whether the change has delivered the anticipated impacts and benefits set out in the original airspace change proposal and decision, and if not to ascertain why and determine the most appropriate course of action.

Close Post Implementation Review, March 19