Sponsor: NATS
Framework briefing held with organisations considering proposal of the change | 22 Jan 2015 |
Sponsor external consultation document (with associated appendices) | 31 Mar 2015 |
Sponsor’s external consultation feedback report | 21 Jul 2015 |
Sponsor’s formal airspace change proposal (date received by CAA) | 27 Jul 2015 |
Operational assessment by CAA | 16 Nov 2015 |
Consultation assessment by CAA | 09 Nov 2015 |
Environmental assessment by CAA | 26 Aug 2015 |
Decision document (CAA change approval) | Jan 2016 |
AIRAC distribution date/AIP amendment | |
Change implementation date | |
PIR initiation date |
Post Implementation Review, March 19
The purpose of the PIR is for the CAA, as the independent regulator, to assess whether the change has delivered the anticipated impacts and benefits set out in the original airspace change proposal and decision, and if not to ascertain why and determine the most appropriate course of action.
Provide page feedback
Please enter your comments below, or use our usual service contacts if a specific matter requires an answer.
Fields marked with an asterisk (*) are required.